PROJECT BERLIN

AREA - Knightsbridge


The project brief was to provide our client with a full turn key solution, working closely with the clients team to provided input during the design development stage to ensure that the finishes and designs were achievable and within the client’s budget and the project programme.

 

SCOPE OF WORKS

 

- Assisting the clients team with LTA approval 

- Full strip out of the existing base build. 

- Reconfiguration of existing partitions 
- Supply and installation of carpets.

- Supply and installation of  timber flooring.

- Supply and installation of specialist wall coverings.

- Application of polished plaster

- Supply and installation of specialist joinery 

- Installation and design of full ME&P

- Installation and design of home automation and AV 

- Design and supply and install of feature stone floor

- Supply and install of bespoke ironmongery 

- Supply and install of leak detection system to all wet areas inline with the landlords requirements.

 

 

DURATION

16 weeks

THE DESIGN STUDIO

4-5, The Greens Buildings, Cambridge Rd, Stansted Mountfitchet, London, CM24 8BZ

WORKING HOURS 

BY APPOINTMENT ONLY 

  • LinkedIn
  • Instagram

LONDON OFFICE

Level 17, Dashwood House, 69 Old Broad,  Street, London, EC2M 1QS

WORKING HOURS 

MONDAY

TUESDAY

WEDNESDAY

THURSDAY

FRIDAY

09:00 - 17:00
09:00 - 17:00
09:00 - 17:00
09:00 - 17:00
09:00 - 17:00